Town of Hempstead Department of Water, Levittown Treatment Facility 2A

Posted on June 15, 2015

Client: Town of Hempstead Department of Water
Location: Levittown Water District, New York
Project Type: Levittown Treatment Facility 2A
Project Period: 2011 - 2012
D&B Project Manager: Philip R. Sachs, P.E.
Project Cost: $4,000,000

Project Description

0715091405-01D&B provided engineering services for the design and construction of water treatment facilities with a capacity of 4.0 MGD.

The treatment facility includes the following treatment systems:

  • Packed Tower Aeration for VOC Removal
  • Sodium Hypochlorite for disinfection
  • Lime Slurry for pH adjustment

A standby diesel generator was provided for emergency electrical power.

Preliminary design reports were prepared for each of the treatment systems and were submitted to the Nassau County Department of Health (NCDH) for approval. Construction phase services included office services and field inspection services. Startup assistance was provided upon completion of the construction work. D&B assisted the Town in obtaining approvals from NCDH for operation.

 0715091410-03       0715091411-02 

See all Profiles related to Water Supply Services